CAPITAL PROJECTS QUARTERLY STATUS REPORT. May 2021
Bobcat Stadium South End Zone Addition. CIP Cost: $16,491,884
This project will remodel a large portion of the existing South End Zone Complex add on to the building for a weight room, sports medicine (training) area, and rehabilitation area. New locker rooms and meeting areas will also be provided in the existing building.
Status: The feasibility study for the Bobcat Stadium South End Zone Addition has been completed. This project is on the CIP and will be initiated pending funding.
Next Milestone: Funding availability.
Bobcat Stadium Seating Anchor Replacement - Delegated Project
Engineer: Datum Engineering
Contractor:TBD
Percent Complete: 0%
Est. Cost:
$2,200,000 !!!
Est. Completion: September 2021(Projected)
This project involves the replacement of bench seat anchors in the football stadium due to galvanic corrosion and wear. Construction documents have been completed, and the project has been released for bid. Construction is anticipated to start in May 2021.
Status: Bidding Phase
Next Milestone: Selection of Contractor